Requirements
1.
Application for permit for construction planning activities (form 1)
(original) If the intended construction project is a large compound, investor has to provide specific information about:
- expected boundaries and perimeter of the land plot
- intended investment project, construction project and capital estimate
- investor's financial ability statement for the project
or
Application for permit for construction planning activities (form 3)
(original) If it is a single construction project.
Investor also has to provide specific information about:
- expected boundaries and perimeter of the land plot
- intended investment project, construction project and capital estimate
- investor's financial ability statement for the project
2.
Outlined cadastral map of the land plot (original)
Time frame
Come back to the office on the date indicated in the receipt of application and, usually, the result is ready for picking up.
Waiting time in queue:
Min. 5mn - Max. 10mn
Attention at counter:
Min. 5mn - Max. 10mn
Waiting time until next step:
Min. 15 days - Max. 20 days
Legal justification
1.
Law on urban planning No.30/2009/QH12 dated 17/6/2009 by the National Assembly No.12
Article 71
2.
Decree 37/2010/ND-CP dated 07/04/2010 regarding preparation, evaluation, approval and management of urban planning
articles 35, 36, 37, 38, 40,
3.
Decision 07/2012/QD-UBND dated 12/03/2012 by BInh Dinh Province People's Committee stipulating protocols on development, evaluation, approval and issue permit for urban planning activities in the province
articles 13, 14, 15..
Additional information
THIS STEP CAN BE PROCEEDED RIGHT AFTER THE INVESTMENT INTENT IS APPROVED.
The notification of fee for processing and issue permit for urban planning activities will be issued and given to the investor on his/her return to collect the approval.
Who certified this information ?
Bao VIET TRAN, Deputy Director,
18/03/2015