Requirements
1.
Application for land location (2 original )
There is no standard format for this type of letter.
2.
Authenticated copy of approval of investment intent (Simple copy + an authentic copy)
3.
Cadastral map of the land plot (original + Simple copy)
Time frame
Waiting time in queue:
Min. 5mn - Max. 10mn
Attention at counter:
Min. 10mn - Max. 15mn
Waiting time until next step:
Min. 7 days - Max. 9 days
Legal justification
1.
Land Law No.45/2013/QH13 dated 29/11/2013 by the National Assembly No.13
articles 52.2, 56.1.đ, 56.1.e, 58.3, 59.1.c, 59.1.d
2.
Decree 43/2014/ND-CP dated 15/05/2014 by the Government specifying the enforcement of a number of provision of the Land Law 45/2013/QH13
articles 14, 60.1, 60.3, 61.1.a, 62, 68.4
3.
Decision 12/2011/QD-UBND dated 02/06/2011 by Binh Dinh Province People's Committee promulgating protocols on orders and coordination mechanism for administrative procedures concerning investment and construction outside industrial and economic zones in Binh Dinh Province
articles 5.2, 5.2, 5.4, 5.5.
4.
Decision 2979/QĐ-CTUBND dated 25/12/2012 by the Chairman of Binh Dinh Province People's Comiittee annoucing newly-promulgated administrative procedures to amend, supplement, replace and cancel some administrative procedures of Binh Dinh Department of Environment and Natural Resources (VN)
Section tionII.I.1
Who certified this information ?
Trung Thanh DANG, Deputy Director,
20/04/2015