Meet with Binh Dinh Department of Investment and Planning (DPI)
Obtain outlined cadastral map of land site  (2)
Obtain certified copies of documents  (2)
Obtain consular-legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain approval of investment intent  (2)
Obtain authenticated copies of investment intent approval  (2)
Obtain investment certificate  (2)
Obtain authenticated copies of investment certificate  (2)
Obtain enterprise registration Certificate (ERC)  (2)
Announce enterprise registration content and notify use of seal sample  (2)
Obtain certificate of tax registration  (2)
Open bank account  (1)
Obtain sectional cadastral map of the land plot  (3)
Obtain approval of land lease intention  (2)
Obtain district people's committee's decisions on land recovery  (9)
Obtain planning license  (4)
Obtain approval of 1/500 scale construction designing plan  (4)
Obtain authenticated copies of approval of 1/500 scale construction designing plan  (2)
Obtain approval of land lease  (3)
Obtain approval of land site boundary  (2)
Obtain land lease contract and land use right certificate  (4)
Obtain authenticated copies of land use rights certificate  (2)
Obtain approval of environment impact assessment report  (5)
Obtain evaluation of conceptual plans  (8)
Obtain approval of fire prevention and fighting plan  (2)
Obtain evaluation of detailed construction plans  (4)
Obtain construction permit  (4)

Preview & Print

Properties
 
66
Collect approval of EIA report
(last modified: 10/4/2015)

Contact details

Entity in charge

Binh Dinh Department of Natural Resources and Environment

08 Hai Ba Trung Street , Quy Nhon
Tel: +84 56 382 0806
Website: http://tinyurl.com/q27kmkl

Unit in charge

Single window office_DONRE

Mon: 07:00-11:30, 13:30-17:00
Tue: 07:00-11:30, 13:30-17:00
Wed: 07:00-11:30, 13:30-17:00
Thu: 07:00-11:30, 13:30-17:00
Fri: 07:00-11:30, 13:30-17:00

Person in charge

Ms Do Chan Tu

Receptionist
Tel: +84 56 381 8624
Email: tudc@stnmt.binhdinh.gov.vn

Expected results

Approval of EIA report Approval of EIA report
Endorsed environment impact assessment report Endorsed environment impact assessment report

Requirements

1. 01 - Libre deuda de patente
Receipt of EIA report evaluation application (original)
This receipt is used throughout the processing of the approval.
2. 01 - Libre deuda de patente
Certification of re-submission of finalized EIA report (original)

Time frame

Waiting time in queue: Min. 5mn - Max. 10mn
Attention at counter: Min. 5mn - Max. 10mn

Who certified this information ?

Trung Thanh DANG, Deputy Director, 07/02/2014

Recourse: Binh Dinh Department of Natural Resources and Environment

Entity in charge

Binh Dinh Department of Natural Resources and Environment

08 Hai Ba Trung Street , Quy Nhon
Tel: +84 56 382 0806
Website: http://tinyurl.com/q27kmkl

Unit in charge

Binh Dinh Department of Natural Resources and Environment's administration office

Mon: 07:00-11:30, 13:30-17:00
Tue: 07:00-11:30, 13:30-17:00
Wed: 07:00-11:30, 13:30-17:00
Thu: 07:00-11:30, 13:30-17:00
Fri: 07:00-11:30, 13:30-17:00

Person in charge

Mr Ho Dac Khanh

Deputy Chief of Office
Tel: +84 56 381 3275, +84 121 359 3891
Email: khanhhd@stnmt.binhdinh.gov.vn
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License