Costs( ver detalles ) |
Timeframe ( ver detalles ) |
||
VND
8395200
|
|
Entity in chargeSub-department of Fire Prevention, Fighting and Rescue65 Ha Huy Tap
, Quy Nhon, Binh Dinh Province
Tel: +84 56 386 9385 |
Unit in chargeConsultation Division_PCCC
|
Person in chargeMr Le Van Hoa
Team leader
Tel: +83 56 386 9386 |
Entity in chargeSub-department of Fire Prevention, Fighting and Rescue65 Ha Huy Tap
, Quy Nhon, Binh Dinh Province
Tel: +84 56 386 9385 |
Unit in chargeConsultation Division_PCCC
|
Person in chargeMr Pham Dinh Trung
Director
Tel: +84 56 386 9281, +84 905 030 114 |
It is assumed that the construction project cost estimate is VND 44,000,000,000. Then the fee rate for evaluation of fire prevention and fighting is 0.0636.. The evaluation charge is calculated as follows:
VND 44,000,000,000 x 0.0636% = VND 27,984,000.
There are three different formulas for the calculation of appraisal fee for fire prevention and fighting section of construction plans depending on the construction cost estimate whether:
LET EXCEL DO THE COMPLICATED CALCULATION FOR YOU IN THE FOLLOWING ATTACHMENT
According to Article 5.2.b of Circular 150/2014/TT-BTC dated 10/10/2014 by the Ministry of Finance, the fee for evaluation of fire prevention and fighting section in the two-step construction plans is divided into two separate payments of 30% and 70% of the total amount at the collection of appraisal results of conceptual plans and then the approval of detailed plans respectively. The entity's bank account is printed in the notification of fee for evaluation of fire prevention and fighting plans.