Costs( ver detalles ) |
Timeframe ( ver detalles ) |
Espera hasta paso siguiente |
||||
VND
1705000
|
|
|
Entity in chargeBinh Dinh Province Department of Construction32 Ly Thuong Kiet
, Quy Nhơn, Binh Dinh Province
Tel: +84 56 382 2882 Website: http://sxd.binhdinh.gov.vn/ |
Unit in chargeCashier office (DoC)
|
Person in chargeMs Duong Thi Tu Trinh |
Cost detail |
Hypothesis |
25
% construction project evaluation charge
-
--
1,705,000
Conceptual plans evaluation fee - 25% x VND 6,820,000
|
Evaluation charge: 6,820,000 |
Entity in chargeBinh Dinh Province Department of Construction32 Ly Thuong Kiet
, Quy Nhơn, Binh Dinh Province
Tel: +84 56 382 2882 Website: http://sxd.binhdinh.gov.vn/ |
Unit in chargeSingle window office_DoC
|
Person in chargeMr Nguyen Danh Dung |
It is assumed that the construction project cost estimate is VND 44,000,000,000. Then the charge rate for evaluation of construction project cost estimate of VND 44 billion is 0.0155 (Tariff for construction project evaluation enclosed in Circular 176/2011/TT-BTC bellow). The evaluation charge is calculated as follows:
VND 44,000,000,000 x 0.0155% = VND 6,820,000. This amount is payable to private individuals or organization conducting the evaluation of construction project whilst the fee for evaluation of conceptual plans is payable to public service agency.
Fee for appraisal of conceptual plan is 25% of construction project evaluation charge as per Article 4.2, Circular 176/2011/TT-BTC.
There are three different formulas for the calculation of appraisal fee of conceptual plans depending on the construction cost estimate whether:
LET EXCEL DO THE COMPLICATED CALCULATION FOR YOU IN THE FOLLOWING ATTACHMENT