Requirements
1.
Application for EIA report evaluation (original)
This is template from Appendix 2.3, Circular 26/2011/TT-BTNMT dated 18/07/2011 specifying some articles of Decree 29/2011/ND-CP providing protocols on strategic environment assessment, environment impact assessment and environment protection plan.
2.
EIA report (7 original )
3.
Comprehensive nvestment project (original)
4.
Authenticated copy of approval of investment intent (original)
5.
Authenticated copy of Investment registration certificate (original)
Time frame
Waiting time in queue:
Min. 5mn - Max. 10mn
Attention at counter:
Min. 5mn - Max. 10mn
Legal justification
1.
Law on Environmental Protection No. 55/2014/QH13 dated 23/06/2014 by the National Assembly No. 13
Article 23.4
2.
Decree 18/2015/ND-CP dated 14/02/2015 by the Government regulating environmental protection planning, strategic environmental assessment, environmental impact assessment and environmental protection plans
articles 14.1.d, 14.2..b, 14.2.c
3.
Circular 26/2011/TT-BTNMT dated 18/07/2011 by the Ministry of Natural Resources and Environment specifying some articles of Decree 29/2011/ND-CP dated 18/04/2011 by the Government re strategic environment assessments, environment impact assessments, environmental protection commitments.
articles 10, 13, 14, 15.
4.
Decision 12/2011/QD-UBND dated 02/06/2011 by Binh Dinh Province People's Committee promulgating protocols on orders and coordination mechanism for administrative procedures concerning investment and construction outside industrial and economic zones in Binh Dinh Province
Article 8
Who certified this information ?
Trung Thanh DANG, Deputy Director,
07/02/2014