List of steps
(Total number of steps: 84)
Meet with Binh Dinh Department of Investment and Planning (DPI)
Obtain outlined cadastral map of land site  (2)
Obtain certified copies of documents  (2)
Obtain consular-legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain approval of investment intent  (2)
Obtain authenticated copies of investment intent approval  (2)
Obtain investment certificate  (2)
Obtain authenticated copies of investment certificate  (2)
Obtain enterprise registration Certificate (ERC)  (2)
Announce enterprise registration content and notify use of seal sample  (2)
Obtain certificate of tax registration  (2)
Open bank account  (1)
Obtain sectional cadastral map of the land plot  (3)
Obtain approval of land lease intention  (2)
Obtain district people's committee's decisions on land recovery  (9)
Obtain planning license  (4)
Obtain approval of 1/500 scale construction designing plan  (4)
Obtain authenticated copies of approval of 1/500 scale construction designing plan  (2)
Obtain approval of land lease  (3)
Obtain approval of land site boundary  (2)
Obtain land lease contract and land use right certificate  (4)
Obtain authenticated copies of land use rights certificate  (2)
Obtain approval of environment impact assessment report  (5)
Obtain evaluation of conceptual plans  (8)
Obtain approval of fire prevention and fighting plan  (2)
Obtain evaluation of detailed construction plans  (4)
Obtain construction permit  (4)

Preview & Print

Properties
 
62
Submit application for evaluation of EIA report
(last modified: 10/4/2015)

Contact details

Entity in charge

Binh Dinh Department of Natural Resources and Environment

08 Hai Ba Trung Street , Quy Nhon
Tel: +84 56 382 0806
Website: http://tinyurl.com/q27kmkl

Unit in charge

Single window office_DONRE

Mon: 07:00-11:30, 13:30-17:00
Tue: 07:00-11:30, 13:30-17:00
Wed: 07:00-11:30, 13:30-17:00
Thu: 07:00-11:30, 13:30-17:00
Fri: 07:00-11:30, 13:30-17:00

Person in charge

Ms Do Chan Tu

Receptionist
Tel: +84 56 381 8624
Email: tudc@stnmt.binhdinh.gov.vn

Expected results

Receipt of EIA report evaluation application 01 - Receipt of EIA report evaluation application
Fee and where to pay is informed 01 - Fee and where to pay is informed

Requirements

1. Application for EIA report evaluation
Application for EIA report evaluation (original)
This is template from Appendix 2.3, Circular 26/2011/TT-BTNMT dated 18/07/2011 specifying some articles of Decree 29/2011/ND-CP providing protocols on strategic environment assessment, environment impact assessment and environment protection plan.
2. EIA report
EIA report (7 original )
3. Comprehensive nvestment project
Comprehensive nvestment project (original)
4. 01 - Libre deuda de patente
Authenticated copy of approval of investment intent (original)
5. Authenticated copy of Investment registration certificate
Authenticated copy of Investment registration certificate (original)

Time frame

Waiting time in queue: Min. 5mn - Max. 10mn
Attention at counter: Min. 5mn - Max. 10mn

Legal justification

1. Law on Environmental Protection No. 55/2014/QH13 dated 23/06/2014 by the National Assembly No. 13
Law on Environmental Protection No. 55/2014/QH13 dated 23/06/2014 by the National Assembly No. 13
Article 23.4
2. Decree 18/2015/ND-CP dated 14/02/2015 by the Government regulating environmental protection planning, strategic environmental assessment, environmental impact assessment and environmental protection plans
Decree 18/2015/ND-CP dated 14/02/2015 by the Government regulating environmental protection planning, strategic environmental assessment, environmental impact assessment and environmental protection plans
articles 14.1.d, 14.2..b, 14.2.c
3. Circular 26/2011/TT-BTNMT dated 18/07/2011 by the Ministry of Natural Resources and Environment specifying some articles of Decree 29/2011/ND-CP dated 18/04/2011 by the Government re strategic environment assessments, environment impact assessments, environmental protection commitments.
Circular 26/2011/TT-BTNMT dated 18/07/2011 by the Ministry of Natural Resources and Environment specifying some articles of Decree 29/2011/ND-CP dated 18/04/2011 by the Government re strategic environment assessments, environment impact assessments, environmental protection commitments.
articles 10, 13, 14, 15.
4. Decision 12/2011/QD-UBND dated 02/06/2011 by Binh Dinh Province People's Committee promulgating protocols on orders and coordination mechanism for administrative procedures concerning investment and construction outside industrial and economic zones in Binh Dinh Province
Decision 12/2011/QD-UBND dated 02/06/2011 by Binh Dinh Province People's Committee promulgating protocols on orders and coordination mechanism for administrative procedures concerning investment and construction outside industrial and economic zones in Binh Dinh Province
Article 8

Who certified this information ?

Trung Thanh DANG, Deputy Director, 07/02/2014

Recourse: Binh Dinh Department of Natural Resources and Environment

Entity in charge

Binh Dinh Department of Natural Resources and Environment

08 Hai Ba Trung Street , Quy Nhon
Tel: +84 56 382 0806
Website: http://tinyurl.com/q27kmkl

Unit in charge

Binh Dinh Department of Natural Resources and Environment's administration office

Mon: 07:00-11:30, 13:30-17:00
Tue: 07:00-11:30, 13:30-17:00
Wed: 07:00-11:30, 13:30-17:00
Thu: 07:00-11:30, 13:30-17:00
Fri: 07:00-11:30, 13:30-17:00

Person in charge

Mr Ho Dac Khanh

Deputy Chief of Office
Tel: +84 56 381 3275, +84 121 359 3891
Email: khanhhd@stnmt.binhdinh.gov.vn