Requirements
1.
Cover letter for re-submission of EIA report (2 original )
2.
Finalized EIA report in compliant with the Evaluation Council's comments (4 original )
with hard covers
3.
Finalized EIA report on CD rom
Time frame
Waiting time in queue:
Min. 5mn - Max. 10mn
Attention at counter:
Min. 5mn - Max. 10mn
Waiting time until next step:
Min. 15 days - Max. 20 days
Legal justification
1.
Law on Environmental Protection No. 55/2014/QH13 dated 23/06/2014 by the National Assembly No. 13
Article 25
2.
Decree 18/2015/ND-CP dated 14/02/2015 by the Government regulating environmental protection planning, strategic environmental assessment, environmental impact assessment and environmental protection plans
articles 14.1.d, 14.6
3.
Circular 26/2011/TT-BTNMT dated 18/07/2011 by the Ministry of Natural Resources and Environment specifying some articles of Decree 29/2011/ND-CP dated 18/04/2011 by the Government re strategic environment assessments, environment impact assessments, environmental protection commitments.
articles 14, 15.
4.
Decision 12/2011/QD-UBND dated 02/06/2011 by Binh Dinh Province People's Committee promulgating protocols on orders and coordination mechanism for administrative procedures concerning investment and construction outside industrial and economic zones in Binh Dinh Province
Article 8.
Who certified this information ?
Trung Thanh DANG, Deputy Director,
07/02/2014