List of steps
(Total number of steps: 41)
Meet with Binh Dinh Economic Zone Administration (BEZA)
Obtain principle agreement for land reservation  (1)
Obtain certified copies of documents  (2)
Obtain consular-legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain investment registration Certificate  (2)
Obtain authenticated copies of the investment registration Certificate  (2)
Obtain enterprise registration Certificate  (2)
Announce enterprise registration and seal specimen on National Business Registration Portal  (2)
Obtain certificate of tax registration  (2)
Open bank account  (1)
Obtain approval of 1/500-scaled detailed plannning  (5)
Obtain land lease contract and certificate of land use rights  (5)
Obtain authenticated copies of land use rights certificate  (2)
Obtain approval of environment protection plan  (3)
Obtain construction permit  (5)

Preview & Print

Properties
 
35
Submit environment protection plan registration file
(last modified: 9/20/2015)

Timeframe ( ver detalles )

Espera hasta paso siguiente

10 mn  -  20 mn
3 days  -  5 days

Contact details

Entity in charge

Binh Dinh Economic Zone Administration (BEZA)

65 Tay Son , Quy Nhon, Binh Dinh Province
Tel: +84 56 364 6257/+84 56 384 6519
Tel. 1: +84 56 384 6616
Email: kktbinhdinh@binhdinh.gov.vn
Website: http://kktbinhdinh.vn/page/en.aspx, http://kktbinhdinh.vn/page/

Unit in charge

One-stop-shop office(BEZA)

Mon: 07:00-11:30, 13:30-17:00
Tue: 07:00-11:30, 13:30-17:00
Wed: 07:00-11:30, 13:30-17:00
Thu: 07:00-11:30, 13:30-17:00
Fri: 07:00-11:30, 13:30-17:00

Person in charge

Ms Vu Hoai Bac

Expert
Tel: +84 56 364 6257
Email: bacvh@kkt.binhdinh.gov.vn

Expected results

Receipt of environment protection plan registration file 01 - Receipt of environment protection plan registration file

Requirements

1. Application for environment protection commitment registration
Application for environment protection commitment registration (original)
2. Environment protection plan
Environment protection plan (3 original )
3. Investment project proposal/Feasibility study report
Investment project proposal/Feasibility study report (original)
4. 01 - Libre deuda de patente
Sectional cadastral map (an authentic copy)

Time frame

Waiting time in queue: Min. 5mn - Max. 10mn
Attention at counter: Min. 5mn - Max. 10mn
Waiting time until next step: Min. 3 days - Max. 5 days

Legal justification

1. Law on Environment Protection No.52/2005/QH11 dated 29/11/2005 by the National Assembly No.11
Law on Environment Protection No.52/2005/QH11 dated 29/11/2005 by the National Assembly No.11
Article 26
2. Decree 80/2006/ND-CP dated 09/08/2006 by the Government detailing and guiding the implementation of some provisions of the Law on Environment Protection
Decree 80/2006/ND-CP dated 09/08/2006 by the Government detailing and guiding the implementation of some provisions of the Law on Environment Protection
articles 9.3, 9.4
3. Decree 21/2008/ND-CP dated 21/02/2008 by the Government amending a number of provisions of Decree 80/2006/ND-CP dated 09/08/2006 specifying and guiding the implementation of some provisions of the Law on Environment Protection
Decree 21/2008/ND-CP dated 21/02/2008 by the Government amending a number of provisions of Decree 80/2006/ND-CP dated 09/08/2006 specifying and guiding the implementation of some provisions of the Law on Environment Protection
articles 7.1.b, 7.1.c
4. Decree 29/2011/ND-CP dated 18/04/2011 specifying protocols on strategic environment assessments, environment impact assessments and  environment protection commitment
Decree 29/2011/ND-CP dated 18/04/2011 specifying protocols on strategic environment assessments, environment impact assessments and environment protection commitment
articles 30.3, 31.3, 31.4, 33
5. Circular 26/2011/TT-BTNMT dated 18/07/2011 by the Ministry of Natural Resources and Environment specifying some articles of Decree 29/2011/ND-CP dated 18/04/2011 by the Government re strategic environment assessments, environment impact assessments, environmental protection commitments.
Circular 26/2011/TT-BTNMT dated 18/07/2011 by the Ministry of Natural Resources and Environment specifying some articles of Decree 29/2011/ND-CP dated 18/04/2011 by the Government re strategic environment assessments, environment impact assessments, environmental protection commitments.
Article 46
6. Decision 2565/QD-CTUBND dated 06/10/2009 by Chairman of Binh Dinh Province People's Committee regarding authorization and task assigned to Binh Dinh Economic Zone Administration (VN)
Decision 2565/QD-CTUBND dated 06/10/2009 by Chairman of Binh Dinh Province People's Committee regarding authorization and task assigned to Binh Dinh Economic Zone Administration (VN)
Article 2.b

Additional information

NB: Investors should refer to the Decree 29/2011/ND-CP, Appendix II list of projects of which environment impact assessment reports are required. Only environment protection commitment is required if your project does not fall into these categories.

Recourse: Binh Dinh Economic Zone Administration (BEZA)

Entity in charge

Binh Dinh Economic Zone Administration (BEZA)

65 Tay Son , Quy Nhon, Binh Dinh Province
Tel: +84 56 364 6257/+84 56 384 6519
Tel. 1: +84 56 384 6616
Email: kktbinhdinh@binhdinh.gov.vn
Website: http://kktbinhdinh.vn/page/en.aspx, http://kktbinhdinh.vn/page/

Unit in charge

Division of Natural Resources and Environment (BEZA)

Mon: 07:00-11:30, 13:30-17:00
Tue: 07:00-11:30, 13:30-17:00
Wed: 07:00-11:30, 13:30-17:00
Thu: 07:00-11:30, 13:30-17:00
Fri: 07:00-11:30, 13:30-17:00

Person in charge

Mr Le Minh Thong

Deputy Head (in charge of the division)
Tel: +84 914 188 915
Email: thonglm@kkt.binhdinh.gov.vn, leminhthongtnmt@gmail.com