List of steps
(Total number of steps: 50)
Meet with Binh Dinh Economic Zone Administration (BEZA)
Obtain principle agreement for land reservation  (1)
Obtain certified copies of documents  (2)
Obtain consular-legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain investment registration Certificate  (2)
Obtain authenticated copies of the investment registration Certificate  (2)
Obtain enterprise registration Certificate  (2)
Announce enterprise registration and seal specimen on National Business Registration Portal  (2)
Obtain certificate of tax registration  (2)
Open bank account  (1)
Obtain approval of 1/500-scaled detailed plannning  (5)
Obtain land lease contract and certificate of land use rights  (5)
Obtain authenticated copies of land use rights certificate  (2)
Obtain environment impact assessment (EIA) report approval  (6)
Obtain conceptual plans appraisal  (5)
Obtain approval of fire protection and fighting plan  (2)
Obtain construction permit  (4)

Preview & Print

Properties
 
34
Prepare EIA report
(last modified: 9/20/2015)

Contact details

Entity in charge

Any environmental engineering consultant service provider

Environment consultantl service providers in Quy Nhon Environment consultantl service providers in Quy Nhon

Expected results

Environment Impact Assessment Report x7 Environment Impact Assessment Report

Requirements

1. Investment project proposal/Feasibility study report
Investment project proposal/Feasibility study report (Simple copy)
2. Investment registration certificate
Investment registration certificate (Simple copy)

Costs

Cost detail

Hypothesis

VND 15,000,000
EIA report making fee - for reference only
Cost which is between VND 70 - 140 million is only applied if investor outsources the production of the EIA report.

Legal justification

1. Law on Environment Protection No.52/2005/QH11 dated 29/11/2005 by the National Assembly No.11
Law on Environment Protection No.52/2005/QH11 dated 29/11/2005 by the National Assembly No.11
articles 18, 19, 20
2. Decree 29/2011/ND-CP dated 18/04/2011 specifying protocols on strategic environment assessments, environment impact assessments and  environment protection commitment
Decree 29/2011/ND-CP dated 18/04/2011 specifying protocols on strategic environment assessments, environment impact assessments and environment protection commitment
articles 13, 14, 15, 16, 17
3. Circular 26/2011/TT-BTNMT dated 18/07/2011 by the Ministry of Natural Resources and Environment specifying some articles of Decree 29/2011/ND-CP dated 18/04/2011 by the Government re strategic environment assessments, environment impact assessments, environmental protection commitments.
Circular 26/2011/TT-BTNMT dated 18/07/2011 by the Ministry of Natural Resources and Environment specifying some articles of Decree 29/2011/ND-CP dated 18/04/2011 by the Government re strategic environment assessments, environment impact assessments, environmental protection commitments.
articles 10, 12

Additional information

In producing an environmental impact assessment report, investors may:
  • 1) do the job themselves if sufficient qualified technical experts are deployed for the task in accordance with Article 16, Decree 29/2011/ND-CP dated 18/04/2011 specifying protocols on strategic environment assessments, environment impact assessments and environment protection commitment; or
  • 2) outsource the EIA report production to any qualified environmental technology consultant service provider if not qualified for the conditions of the Decree.
In case of outsourcing the production of an EIA report, the cost is between VND 70 and 140 million.
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License