List of steps
(Total number of steps: 48)
Meet with Binh Dinh Economic Zone Adminstration (BEZA)
Obtain a principle agreement for land reservation  (1)
Obtain certified copies of documents  (2)
Obtain consular-legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain investment registration Certificate (IRC)  (2)
Obtain authenticated copies of the investment registration Certificate  (2)
Obtain enterprise registration Certificate  (2)
Announce enterprise registration and seal specimen on National Business Registration Portal  (2)
Obtain certificate of tax registration  (2)
Open bank account  (1)
Sign land lease agreement and obtain land use right certificate  (7)
Obtain authenticated copies of land use rights certificate  (2)
Obtain approval of environment impact assessment (EIA) report  (6)
Obtain conceptual plans appraisal  (6)
Obtain approval of fire protection and fighting plan  (2)
Obtain construction permit  (4)

Preview & Print

Properties
 
37
Prepare conceptual plans
(last modified: 9/27/2015)

Expected results

Conceptual plans Conceptual plans
Technical specification of conceptual plans Technical specification of conceptual plans
Construction designing competency report Construction designing competency report

Requirements

1. 01 - Libre deuda de patente
Sectional cadastral map (Simple copy)
2. Land use rights certificate
Land use rights certificate (Simple copy)

Costs

Cost is only applied if investor outsources the production of conceptual plans.

Legal justification

1. Law on construction No. 50/2014/QH13 dated 18/06/2014 passed by the 13th National Assembly
Law on construction No. 50/2014/QH13 dated 18/06/2014 passed by the 13th National Assembly
articles 52.3, 55, 57.3, 57.4, 57.5, 58
2. Law 38/2009/QH12 dated 19/06/2009 amending and supplementing some provisions of laws relating to captial construction projects
Law 38/2009/QH12 dated 19/06/2009 amending and supplementing some provisions of laws relating to captial construction projects
Article 1.1
3. Decree 12/2009/ND-CP dated 12/02/2009 by the Government regarding management of construction projects
Decree 12/2009/ND-CP dated 12/02/2009 by the Government regarding management of construction projects
articles 8, 11.3, 13.1.b, 16.1.a, 16.2.b
4. Decree 15/2013/ND-CP dated 06/02/2013 by the Government regarding quality management of construction works
Decree 15/2013/ND-CP dated 06/02/2013 by the Government regarding quality management of construction works
Article 20

Additional information

Please refer to article 13.1.b of Decree 12/2009/ND-CP on construction project management for further information on when two- or three-step construction designing is required.
Under circumstances where one-step construction designing is required, investors only have to produce detailed construction plans and techno economic feasibility reports for their application of construction permits.
Investors are eligible for producing construction plans themselves if they employ or deploy sufficient qualified architects and civil engineers in accordance with Article 36 of Decree 12/2009/ND-CP on management of construction projects. Otherwise, they have to outsource for the production of construction plans, in which case costs will incur.

NOTE: The construction cost estimate provided in the 'Technical specification of conceptual plans' will be used for calculating charge for construction project evaluation and then fee for appraisal of conceptual plans in later steps.