Meet with Binh Dinh Economic Zone Adminstration (BEZA)
Obtain a principle agreement for land reservation  (1)
Obtain certified copies of documents  (2)
Obtain consular-legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain investment registration Certificate (IRC)  (2)
Obtain authenticated copies of the investment registration Certificate  (2)
Obtain enterprise registration Certificate  (2)
Announce enterprise registration and seal specimen on National Business Registration Portal  (2)
Obtain certificate of tax registration  (2)
Open bank account  (1)
Sign land lease agreement and obtain land use right certificate  (7)
Obtain authenticated copies of land use rights certificate  (2)
Obtain approval of environment impact assessment (EIA) report  (6)
Obtain conceptual plans appraisal  (6)
Obtain approval of fire protection and fighting plan  (2)
Obtain construction permit  (4)

Preview & Print

Properties
 
43
Submit application file for approval of fire protection and fighting plan
(last modified: 9/27/2015)

Timeframe ( ver detalles )

Espera hasta paso siguiente

20 mn  -  40 mn
15 days  -  20 days

Contact details

Entity in charge

Sub-department of Fire Prevention, Fighting and Rescue

65 Ha Huy Tap , Quy Nhon, Binh Dinh Province
Tel: +84 56 386 9385

Unit in charge

Consultation Division_PCCC

Mon: 07:00-11:30, 13:30-17:00
Tue: 07:00-11:30, 13:30-17:00
Wed: 07:00-11:30, 13:30-17:00
Thu: 07:00-11:30, 13:30-17:00
Fri: 07:00-11:30, 13:30-17:00

Person in charge

Mr Le Van Hoa

Team leader
Tel: +83 56 386 9386

Expected results

Receipt of application for fire fighting and protection plan approval 01 - Receipt of application for fire fighting and protection plan approval

Requirements

1. 01 - Libre deuda de patente
Application for evaluation and approval of fire protection and fighting plans (2 original )
2. Finalized conceptual plans
Finalized conceptual plans (2 original )
3. Detailed plans (printed on A1 or A2 sized-paper)
Detailed plans (printed on A1 or A2 sized-paper) (2 original )
or Technical designs (printed on A1 or A2 sized paper)
Technical designs (printed on A1 or A2 sized paper) (2 original )
4. 01 - Libre deuda de patente
Sectional cadastral map (2 authentic copies)
5. Authenticated copy of land use rights certificate
Authenticated copy of land use rights certificate (2 authentic copies)
6. Authenticated copy of investment certificate
Authenticated copy of investment certificate (2 authentic copies)

Time frame

Waiting time in queue: Min. 5mn - Max. 10mn
Attention at counter: Min. 15mn - Max. 30mn
Waiting time until next step: Min. 15 days - Max. 20 days

Legal justification

1. Law on Fire Protection and Fighting No.27/2001/QH10 dated 29/06/2001 by the National Assembly No.10
Law on Fire Protection and Fighting No.27/2001/QH10 dated 29/06/2001 by the National Assembly No.10
articles 15, 16.1
2. Decree 35/2003/ND-CP dated 04/04/2003 by the Government specifying the implementation of a number of provisions of the Law on fire fighting and prevention
Decree 35/2003/ND-CP dated 04/04/2003 by the Government specifying the implementation of a number of provisions of the Law on fire fighting and prevention
Article 14
3. Decree 46/2012/ND-CP dated 22/05/2012 amending, supplementing some provisions of Decree 35/2003/ND-CP specifying the implementation of some provisions of the Law on Fire Prevention and Fighting and Decree 130/2006/ND-CP dated 08/11/2006 specifying compulsory insurance on fire and explosion
Decree 46/2012/ND-CP dated 22/05/2012 amending, supplementing some provisions of Decree 35/2003/ND-CP specifying the implementation of some provisions of the Law on Fire Prevention and Fighting and Decree 130/2006/ND-CP dated 08/11/2006 specifying compulsory insurance on fire and explosion
Article 3
4. Circular 04/2004/TT-BCA dated 31/04/2004 by the Ministry of Police guiding the implemnetation of Decree 35/2003/ND-CP dated 04/04/2003 by the Government specifying the emplementation of some provisions of the law on fire fighting and prevention
Circular 04/2004/TT-BCA dated 31/04/2004 by the Ministry of Police guiding the implemnetation of Decree 35/2003/ND-CP dated 04/04/2003 by the Government specifying the emplementation of some provisions of the law on fire fighting and prevention
Article IV.

Recourse: Sub-department of Fire Prevention, Fighting and Rescue

Entity in charge

Sub-department of Fire Prevention, Fighting and Rescue

65 Ha Huy Tap , Quy Nhon, Binh Dinh Province
Tel: +84 56 386 9385

Unit in charge

Consultation Division_PCCC

Mon: 07:00-11:30, 13:30-17:00
Tue: 07:00-11:30, 13:30-17:00
Wed: 07:00-11:30, 13:30-17:00
Thu: 07:00-11:30, 13:30-17:00
Fri: 07:00-11:30, 13:30-17:00

Person in charge

Mr Pham Dinh Trung

Director
Tel: +84 56 386 9281, +84 905 030 114
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License